Agricultural Waste System
Organization
Typical Steps to Implement an Ag Waste System include:
- Site Visit - Engineer, fiscal sponsor/investor
and producer/client meet to discuss possible scenarios.
- Survey - The area will be surveyed
using GPS Equipment and/or Total Station equipment to
create a topographic map to determine drainage patterns.
- Preliminary Design- Using the topographic
map, a system layout, and cost estimate will drafted and
presented to the producer and fiscal sponsor if applicable.
- Meeting - The engineer, fiscal sponsor
if applicable, and producer will meet to talk about the
preliminary design; possible problems, alternatives and/or
questions will be addressed at this time before final
design and bid packets are made.
- Final Design - Final Design is presented
to the producer for approval; when design is signed bid
packets are assembled, and then contractors are solicited
for bids (upon governing agency approval - e.g. health
department in North Dakota).
- Stakeout - Area is staked out for
contractors per design.
- Quality Control - Clay liners and
cement pours are tested to insure standards are met.
- Final Approval - After construction
is complete the engineer inspects the system, performs
an as-built survey and composes a report for the governing
agency applicable if necessary, and producer to certify
the system has been constructed as per plans and specifications.
Government Agencies:
Possible Cost Share Assistance:
- NRCS
- Local SCD or SWCD/319 Program
Components
View
slideshow
|
| |